Concrete Containment Area - Southampton, MA

Dscn0094 Pb070012 Pb080005

Building of a Spray Containment area to meet future state regulations

For environmental reasons and future state regulations, our customer requested Hartley Bros. Landscaping build a spray containment area for his business.  In preparation for the concrete to be poured, the sub grade was leveled, the outside edge of the concrete pad area raised up, the rebar set according to plan, and 10-12 inches of processed gravel compacted.  Concrete was poured for the spray containment area, chemical shed area, and the sono-tubes.  The inspections required will be completed by the Natural Resources Conservation Service (NRCS).  The spray containment area channels water to a separate 300 gallon plastic tank by E.J. Prescott.

 